The Project Schedule of Binh Duong Industrial Park

10.07.2011

I/The estimated project schedule:

From year 2005 to 2020 including:

  • Construction of general infrastructure, necessary works, Industrial Parks and service areas in the period of 2005-2010.
  • Construction of the new residential area in the period of 2005-2020.

II/ Schedule until December, 2009:

To complete the construction of:

  • 7 main road routes with total length of 35 km
  • 3 drainage channel routes with total length of 24 km
  • Technical works as per the detailed planning of resettlement areas: Phu Chanh, Phu My, Dinh Hoa, Hoa Loi
  • 3 markets, each uses an area of nearly 5,000 m2.
  • 3 wastewater treatment plants with the capacity of 1,000 m3/day and night for 3 resettlement areas.

Finishing investing in infrastructure construction: power, water, and telecommunication supply.

Industrial investment attraction:

  • VSIP 2 Industrial Park, scale of 343 ha, has attracted 117 investment projects.
  • Dai Dang Industrial Park: scale of 274 ha, has attracted 38 investment projects.
  • Song Than 3 Industrial Park, scale of 533 ha, has attracted 25 investment projects
  • Kim HuyIndustrial Park: scale of 205 ha, has attracted 9 investment projects.
  • Phu GiaIndustrial Park, scale of 133 ha, has attracted 1 investment project.
  • Dong An 2Industrial Park: scale of 158 ha, has attracted 15 investment projects.
  • The project of Viet Nam – Singapore 2 expanded Industrial Park has been approved with the scale of 1,723 ha:

Currently the company has been completing the approval procedures of the detailed planning, design, total estimated costs to construct main works in advance.

Urban area development:

  • October 31, 2008: Binh Duong People’s Committee approved the detailed planning at 1:2000
    scale
  • June 1, 2009: Binh Duong People’s Committee approved the detailed planning at 1:500 scale (Area 1: 709,6086 ha)
  • Currently the detailed planning at 1:500 scale is being prepared (Area 2: 37,2348 ha)